Contract Priorities
A contract is given a priority so it can be calculated which price is used on a sales order.
A higher priority price takes precedence when adding a line to an entry.
Examples

EXAMPLE
A customer has two contracts set up – Contract A and Contract B.
Contract | Contract A | Contract B |
---|---|---|
Item | 00215X | 00215X |
Price | £5.99 | £9.99 |
Priority | 1 | 10 |
Contract B has a higher priority, so the price is £9.99.
EXAMPLE
A customer has two contracts set up – Contract A and Contract B.
Contract | Contract A | Contract B |
---|---|---|
Item | 00215X | 00215X |
Price | £5.99 | £9.99 |
Priority | 5 | 5 |
Both contracts have the same priority. Horizon will pick up Contract A as it has the cheaper price for the customer.